The 6989 "Wightwick Hall" Restoration Group.
Dedicated to putting 6989 back in steam.


HomePrivacy PolicyHistory of 6989Restoration Group NewsFriends of 6989 Wightwick HallWork in Progress

Work in Progress

steamtest2.jpg

The safety valves of 6989's boiler lift for the first time since July 1964. Photo Chris Tayler.

NEWS FROM CHARLIE JONES - OUR CHIEF ENGINEER - OCTOBER 2018:

Work on refurbishing the boiler is complete and out of frames hydraulic and steam tests were successfuly completed and signed off by our boiler inspector. The boiler is back in the frames and we are in the final stages of reassembling the loco ready for an in frames test during October 2018.Lining out is completed and a final coat of varnish is being applied as weather permits.

'Owsden Hall's' tender is ready to run and work has recommenced on our tender tank.

Charlie

SCHEDULED WORKING PARTY DATES 2018:

 In addition to the following dates we often work additional days, watch out for email notifications.

* Check with Rod or Charlie if they will be working this day.

 21 and 22* Oct 2018

18 and 19* Nov 2018

16 and 17* Dec 2018

 

PROGRESS AS AT 14 OCTOBER 2018.

CURRENT WORKING PARTY:

Charlie Jones (Team Leader), Jeff Jackson, Rod Wallis, Chris Tayler, John Spaull, Allan Vessey, Mike Barclay, Ian Mackenzie, Graham Hart, Steve Underhill (boilersmith), Graham Hope (painter).

Work in Progress:
 
The loco is reassembled and we are in the final stages of preparing 6989 for an in frames steam test. Work to be completed after steam test:
 
    Fit firebrick arch. In stock.
    Fit spark arrester. Constructed ready to fit.
    Fit firehole door deflector plate. In stock.
    Set spring tensions.
    Fitness to run inspection.
      Check all systems, adjust and fix snags arising.
      Make and fit copper pipe from Masons valve to train steam heat pipe.
    Final varnish coat to driver's side of loco.
    Continue construction of 6989's tender tank.
 
CAN YOU HELP?
We are always in need of volunteers to assist with the restoration. You do not have to be a locomotive engineer - although it would be great if you are - there is plenty to do for all abilities. See the dates when we will be on site above. If you want to help you need to be a member of the Quainton Railway Society - for insurance purposes. Interested? Contact Charlie Jones on 01525 635860, or Jeff Jackson on 01278 781649 (before 20:00).  

 

image711chap6paintfinished14Oct18RW.jpg

14 October2018. Paintwork and lining completed.

Photo R Wallis.

 

 

image712chap6tenderandlococonnected14oct18rw.jpg

14 October 2018.  loco and tender coupled.

Photo R Wallis.

image689chap6sprinklervalve28aug18gh.jpeg

28 August 2018. Watering and sprinkler valves plumbed in.

Photo G Hart.

image708chap6cabfloor9oct18cj.jpg

9 October 2018. Floor completed.

Photo C Jones.